Knowledge Base

Retrofit & Conversion Engineering — Technical Research

Draft Medium Research 5,383 words Created Mar 4, 2026

Vessel Retrofit Engineering — Aframax Tanker to Plasma Processing Vessel

Converting a second-hand Aframax tanker (80,000-120,000 DWT) into a mobile plasma processing station for ocean plastic. This document covers what gets stripped, what gets built, what gets installed, and what it costs — grounded in real FPSO conversion data and shipyard precedent.

Vessel class: Aframax (LOA ~245m, beam ~44m, depth ~21m) Target conversion: Plasma gasification vessel, 5-10 TPD PRRS, 28-day operating cycles, 1,000nm from Honolulu Analogous industry: FPSO (Floating Production Storage and Offloading) tanker conversions


1. What Gets Stripped

An Aframax crude oil tanker has systems designed for loading, transporting, and discharging crude oil. Most of these are irrelevant or actively harmful to a plasma processing vessel. The conversion strip-out is substantial.

Systems Removed Entirely

SystemWhy It Goes
Cargo pumping systemCentrifugal/deepwell cargo pumps in each tank, pump room, associated piping. Designed to move crude oil. No crude oil on this vessel. All removed. Estimated 200-400 tonnes of equipment and piping.
Crude Oil Washing (COW) systemFixed/portable tank cleaning machines, COW piping, heaters. Required by MARPOL for crude tankers. Completely irrelevant. Removed.
Inert Gas System (IGS)Flue gas scrubber, IG fans, deck water seal, distribution piping. Keeps cargo tanks inert to prevent explosion. No volatile cargo = no need. Removed. Note: if any tanks are repurposed for syngas buffer storage, a purpose-built inerting system would be installed instead.
Cargo heating systemSteam coils in cargo tanks, heating medium (thermal oil or steam) circuits. Keeps heavy crude pumpable. Removed.
Cargo tank coatingsExisting tank coatings (epoxy or bare steel) may need blasting and recoating depending on repurposed use.
Cargo manifold and loading armsMidship manifold, reducers, hoses. Replaced with collection system receiving infrastructure.
Slop tanks (dedicated)Two slop tanks typically fitted aft of cargo block. May be repurposed as waste water holding tanks rather than removed.
Venting system (cargo)PV valves, mast risers, vent headers for cargo tanks. Removed and replaced with ventilation appropriate to new tank usage.
Ballast treatment systemModern tankers have ballast water treatment. Retained but may need relocation or upgrade.

Systems Retained / Modified

SystemStatus
Main engine and propulsionRetained. The vessel must transit to/from the GPGP and reposition within it. Aframax tankers typically have a single slow-speed two-stroke diesel (MAN B&W or similar), 12,000-16,000 kW. Adequate for 14-15 knot transit speed. Service/overhaul during conversion.
Steering gearRetained. Serviced and overhauled.
Navigation and bridge systemsRetained and upgraded. Radar, ECDIS, AIS, GMDSS — all kept. Add satellite comms upgrade, weather routing.
Ballast systemRetained and modified. Ballast tanks, pumps, and piping retained. Ballast plan recalculated for new loading condition (heavy topside equipment vs. distributed cargo weight).
Accommodation blockRetained and likely expanded. Aframax tankers typically have accommodation for 25-30 crew. A processing vessel may need 35-50 (operators, maintenance, collection crew). See Section 3.
Engine room systemsRetained and modified. Generators, switchboards, air compressors, purifiers, workshop — all retained. Electrical generation likely supplemented with syngas generators.
Fire-fighting systemsRetained and significantly upgraded. Existing CO2 and foam systems kept for engine room. New fire protection systems for processing deck (plasma reactor area, syngas handling).
Freshwater generatorRetained or replaced. Existing evaporator or RO unit retained if capacity sufficient. Likely supplemented — see Section 3.
Deck cranesLikely removed and replaced. Tanker cranes (if fitted) are provision/stores cranes, typically 5-10 tonne SWL. Processing vessel needs heavier capacity for debris handling. New crane pedestals required.

Weight Impact of Strip-Out

Removing the cargo handling systems, COW, IGS, and associated piping yields an estimated 500-800 tonnes of removed deadweight. This provides margin for new processing equipment installation but also changes the vessel's lightship weight and stability characteristics — requiring a full inclining experiment and stability recalculation post-conversion.


2. Structural Modifications

This is where the heavy steel work happens. An Aframax tanker deck is designed for distributed liquid cargo loads, not concentrated heavy equipment loads. Every major piece of topside equipment needs a proper foundation, and the entire deck arrangement changes.

Major Structural Work Items

2.1 Deck Reinforcement for Processing Equipment

The main deck over the cargo tank area becomes the processing deck. Tanker main decks are designed for:

  • Distributed cargo pressure from below (hydrostatic)
  • Walking/access loads from above (minimal — typically 1.7 kN/m2)
  • Pipe stress from cargo piping
Processing equipment imposes concentrated point loads of 50-200+ tonnes in relatively small footprints. The deck structure must be reinforced with:
  • New deck stiffeners (increased scantlings under equipment)
  • Pillar supports through to inner bottom or tank top structure
  • Stools and grillage foundations for reactor, generators, and syngas train
  • Doubler plates in high-stress areas
Estimated new steelwork for deck reinforcement: 800-1,200 tonnes

2.2 Reactor Foundation

The PRRS plasma reactor is the heaviest single item. Based on comparable plasma gasification units at 5-10 TPD scale (see Section 3), the reactor module with refractory lining is estimated at 80-150 tonnes. The foundation must:

  • Distribute load to hull primary structure (transverse web frames, longitudinal girders)
  • Accommodate thermal expansion (the reactor operates at 1,500-5,000°C internally)
  • Include vibration isolation mounts
  • Provide for secondary containment (slag/melt escape)
  • Route exhaust stack through any overhead structures
Foundation design: reinforced grillage of I-beams welded to deck and supported by new pillars to tank top. Estimated foundation steelwork: 80-120 tonnes.

2.3 New Bulkheads and Fire/Blast Walls

The processing deck must be subdivided into hazard zones:

  • Reactor zone — highest hazard, blast-rated walls on 3 sides
  • Syngas handling zone — Zone 1 (explosive atmosphere possible during normal operation)
  • Electrical zone — switchgear room, pressurized to prevent gas ingress
  • Collection/receiving zone — wet, mechanical hazard
  • Accommodation safety zone — protected from all processing hazards
Fire and blast walls rated to H-120 (hydrocarbon fire, 120 minutes) or equivalent. Blast-rated walls to withstand syngas deflagration overpressure (typically designed for 0.2-0.5 bar overpressure).

Estimated bulkhead/firewall steelwork: 300-500 tonnes

2.4 Exhaust Stack Routing

The syngas engine exhaust and any reactor off-gas bypass must be routed to a safe discharge point. On an FPSO this is the flare tower — on The Claw it's the exhaust stack system. Requires:

  • Structural tower/mast for elevated discharge (30-40m above deck for dispersion)
  • Self-supporting or guyed steel structure
  • Insulated exhaust ducting from syngas engine and reactor emergency vent
  • Foundation stools on main deck with guy wire attachment points
Estimated stack structure steelwork: 50-80 tonnes

2.5 Crane Pedestals

Processing vessel needs heavy-lift capability for debris collection and equipment maintenance:

  • 2x knuckle-boom cranes (25-40 tonne SWL each) for debris handling, port/starboard
  • 1x provision crane (5-10 tonne SWL) for stores and personnel transfer
Each crane pedestal requires a reinforced foundation extending down to the hull's transverse web frame structure. Pedestals typically 3-5m diameter, 3-4m high, 15-30 tonnes each.

Estimated crane pedestal steelwork: 60-90 tonnes

2.6 Helipad Structure

An offshore-rated helipad per CAP 437 / ICAO Annex 14 standards for medium helicopter (AW139 or S-92 class):

  • D-value: ~17m (AW139) to ~20m (S-92)
  • Helideck diameter/size: minimum 1.0 x D-value, so 20-22m
  • Structure: aluminium or steel deck plate on steel support structure
  • Location: forward (bow area, clear of exhaust plume and processing equipment)
  • Structural weight: helideck itself ~40-60 tonnes (aluminium deck on steel support)
  • Design loads: 12-15 tonne maximum helicopter weight + 2.5x dynamic landing factor
  • Additional: helicopter refuelling system, foam fire-fighting, lighting (HAPI, perimeter, flood), windsock, netting
The bow of an Aframax tanker may need significant reinforcement — the forecastle structure was designed for sea loads and mooring equipment, not helicopter landing loads.

Estimated helipad structure steelwork: 80-120 tonnes (including substructure reinforcement)

2.7 Accommodation Extension

If existing crew accommodation (25-30 persons) is insufficient, a new accommodation module is installed — typically a pre-fabricated multi-deck module lifted onto an extended poop deck or built above the existing accommodation block.

Estimated accommodation module steelwork: 100-200 tonnes (for +20 person extension)

Total New Steelwork Estimate

CategoryTonnes
Deck reinforcement / foundations800 - 1,200
Reactor foundation (specific)80 - 120
Bulkheads and fire/blast walls300 - 500
Exhaust stack structure50 - 80
Crane pedestals60 - 90
Helipad and substructure80 - 120
Accommodation module structure100 - 200
Miscellaneous (access ways, ladders, handrails, pipe supports)200 - 400
Total1,670 - 2,710
Working estimate: ~2,000 tonnes of new steelwork.

For context, a typical Aframax-to-FPSO conversion involves 3,000-6,000 tonnes of new steelwork. The Claw's conversion is simpler (no turret, no risers, no subsea interfaces, no gas compression trains at FPSO scale), but still substantial. The FPSO data point of ~5,500 tonnes for a full Aframax conversion (from SPE/OTC papers) serves as an upper bound.


3. Equipment Installation

3.1 PRRS Plasma Reactor Unit

Supplier: PyroGenesis (Montreal, Canada) System: PRRS (Plasma Resource Recovery System) — 5-10 TPD capacity Technology: Two-step plasma gasification with syngas recovery

ParameterEstimateBasis
Capacity5-10 TPD (start at 5, design for 10)PyroGenesis PRRS product range (1-100 TPD modules)
Footprint150-250 m2 (including gas cleanup)Scaled from PAWDS 65 m2 at ~5 TPD, plus cleanup train
Weight80-150 tonnes (reactor + refractory)Estimated from comparable plasma gasification systems — 10 TPD unit at NCKU Taiwan, InEnTec PEM systems
Form factorModular, ISO container-skid mountedPyroGenesis PRRS is designed as containerized/transportable system (confirmed: 10.5 TPD Hurlburt Field system was ISO-container-skid-mounted)
Power draw0.8-1.1 MWh/tonne of feedstockPer energy-balance.md research: 0.817 MWh/ton at 10 TPD scale
Operating temp1,500-5,000°C in plasma zonePyroGenesis standard plasma torch range
OutputSyngas (H2 + CO) + vitrified slagStandard PRRS output
Foundation requirements: Reinforced grillage on deck, thermal isolation, vibration mounts, secondary containment for slag. Must be located centrally on the cargo deck area for optimal weight distribution and access to syngas train.

Procurement note: PyroGenesis has delivered 4 PAWDS systems to the US Navy (Ford-class carriers) and designed the 10.5 TPD PRRS for Hurlburt Field USAF base. They are the only qualified supplier with proven marine plasma experience. Budget estimate for the PRRS unit: $8-15M (estimated from PAWDS pricing of ~$5.5M per unit for the smaller naval system, scaled up).

3.2 Syngas Cleanup Train

Raw syngas from plasma gasification contains particulates, tars, acid gases (HCl, H2S from chlorinated/sulfur-containing plastics), and trace metals. Must be cleaned before engine use.

ComponentPurposeEst. WeightEst. Footprint
Cyclone separatorRemove coarse particulates5-10 t15 m2
Quench towerCool syngas from 800-1000°C to 200°C15-25 t20 m2
Wet scrubberRemove acid gases (HCl, H2S, SOx)10-20 t25 m2
Baghouse / fabric filterRemove fine particulates8-15 t20 m2
Activated carbon bedRemove trace metals, dioxins5-10 t10 m2
Syngas coolerFinal cooling to engine inlet temp (~40°C)5-10 t10 m2
Condensate separatorRemove water from cooled syngas3-5 t5 m2
Syngas blower/compressorDeliver syngas at engine inlet pressure3-8 t10 m2
Total cleanup train54-103 t~115 m2
The cleanup train is typically arranged linearly, following the gas flow path. On a tanker deck with ~200m of cargo block length, there is ample space. The challenge is weight concentration — each component needs its own foundation grillage.

3.3 Syngas Engine / Generator

Purpose: Convert cleaned syngas to electricity for station self-sufficiency.

Primary candidate: INNIO Jenbacher Type 6 (J612/J616/J620)

  • Jenbacher engines are proven on syngas, landfill gas, and low-calorific gases
  • Type 6 range: 1.8-4.5 MWe
  • Jenbacher J620 GS (syngas variant): ~3.3 MWe electrical output
ParameterSpecification
ModelJenbacher J620 GS (syngas rated) or equivalent
Electrical output2-3 MW (matches station demand — see energy-balance.md)
Weight~85-100 tonnes (engine + generator + baseframe)
Footprint~120 m2 (including service clearances)
FoundationVibration-isolated grillage on deck, double-elastic mounting
ExhaustRouted to stack, catalytic converter for CO/NOx
FuelCleaned syngas from cleanup train
Backup fuelMarine diesel (dual-fuel capability for startup/emergency)
CoolingSeawater-cooled heat exchangers (standard marine arrangement)
Budget estimate: $2-4M for the genset package (engine, generator, controls, switchgear interface).

Alternative candidates: Caterpillar CG260 series (syngas capable, 2-4 MW range), MAN gas engines. Jenbacher has the strongest track record on non-standard gas compositions.

3.4 Electrical Distribution and Switchgear

The existing tanker electrical system is designed for ~3-5 MW of generation capacity (diesel generators powering cargo pumps, accommodation, and engine room). The conversion must:

  • Add new main switchboard section for syngas generator connection
  • Install bus-tie breakers between existing diesel generators and syngas generator for seamless power transfer
  • New motor control centers (MCCs) for processing equipment (reactor, conveyors, cranes, shredders)
  • Emergency generator — existing tanker emergency generator retained, but may need uprating
  • Power management system (PMS) — new PMS to manage load sharing between syngas and diesel generators
  • Variable frequency drives (VFDs) for major motor loads (pumps, conveyors, shredders)
  • Transformer and distribution for accommodation and low-voltage systems
  • Hazardous area electrical equipment — all equipment in syngas zones must be Ex-rated (ATEX/IECEx Zone 1/2)
Weight estimate: 30-50 tonnes (switchgear, transformers, cable, cable trays) Budget estimate: $3-6M

3.5 Collection Equipment

The vessel needs to collect plastic debris from the ocean surface. This is an area where The Claw differs most from an FPSO (which receives product from subsea).

ComponentSpecificationEst. WeightEst. Cost
2x Knuckle-boom cranes25-40t SWL, offshore-rated (Liebherr, Palfinger, NOV)30-50t each$2-4M each
Conveyor systemReceiving hopper → shredder → dewatering → reactor feed. ~100m total belt/screw conveyor. Enclosed, corrosion-resistant.40-60t$1-2M
Shredder/grinderIndustrial dual-shaft shredder for mixed ocean debris including fishing nets. 5-10 TPH capacity (well above reactor feed rate, to allow batch collection).20-30t$0.5-1M
Dewatering systemScrew press or centrifuge to remove saltwater. Waste heat from reactor exhaust used for secondary drying.10-20t$0.3-0.5M
Debris collection nets/boomsDeployable boom system or net trawl arrangement. Stored on deck, deployed by cranes.10-20t$0.5-1M
Workboat/RIB1-2 rigid inflatable boats for collection support and boom deployment. Davit-launched.3-5t each$0.1-0.2M each
Davits2x gravity/pivot davits for workboat launch/recovery5-10t each$0.2-0.3M each
Receiving hopperDeck-level receiving hopper with drainage, feeding conveyor intake10-15t$0.1-0.2M
Total collection systems~170-260t$6-12M

3.6 Helipad and Aviation Systems

ComponentSpecification
Helideck22m diameter aluminium deck on steel substructure, CAP 437 compliant
Design helicopterAW139 or S-92 (medium category, typical offshore crew change helicopter)
HAPI lightingHelicopter Approach Path Indicator
Perimeter lightingFlush-mounted green perimeter lights
FloodlightsFor night operations
Status lightsRed (deck not available) / Green (clear to land)
WindsockIlluminated, visible from approach path
Fire suppressionFoam monitors (minimum 2), agent capacity per CAP 437 (typically AFFF)
Fuel systemAVGAS/JET-A1 storage and dispensing (if helicopter refuelling provided)
Deck nettingSafety netting around helideck perimeter
Motion monitoringHelideck monitoring system (HMS) for vessel motion limits
Weight: 40-60 tonnes (deck + substructure) Budget: $2-4M (structure, lighting, fire systems, monitoring)

3.7 Accommodation Module

Existing Aframax accommodation typically provides for 25-30 persons. The processing vessel likely needs 35-50 persons:

  • 10-15 vessel crew (navigation, engine room, deck)
  • 8-12 processing plant operators (24/7 shift work, 3 shifts)
  • 4-6 maintenance/electrical technicians
  • 2-4 collection system operators
  • 2-3 HSE / medic / admin
  • 2-4 spare berths (visitors, class surveyors, supernumeraries)
If accommodation is insufficient, a pre-fabricated accommodation module (Living Quarters or "LQ") is installed. These are commonly used in offshore and are available from specialist manufacturers (Apply Leirvik, Wuchuan, CIMC Raffles).

ParameterSpecification
Additional capacity+20-25 persons
Decks2-3 storey module
FacilitiesSingle/double cabins, galley/mess, recreation, laundry, offices, hospital
Weight200-400 tonnes (fully outfitted)
Footprint20m x 15m per deck (approximate)
StandardSOLAS compliant, classed to same notation as vessel
Budget$5-10M

3.8 Water Maker and Utility Systems

SystemPurposeEst. Cost
Reverse osmosis water maker20-40 m3/day freshwater production (replace or supplement existing)$0.3-0.5M
Sewage treatment plantFor expanded crew (50-person IMO-compliant)$0.2-0.4M
HVAC upgradeAdditional cooling/ventilation for processing areas and expanded accommodation$0.5-1M
Compressed air systemInstrument air and utility air for processing equipment$0.2-0.3M
Potable water treatmentUV/chlorination for domestic water$0.05-0.1M
Satellite communicationsVSAT for operational data, crew welfare, remote monitoring$0.3-0.5M
Waste water treatmentFor process water from dewatering (salt water + plastic residue), cannot discharge untreated$0.3-0.5M

4. FPSO Conversion Precedents

The Claw's conversion is not an FPSO, but the FPSO industry is the closest analogue — both involve taking a trading tanker and converting it into a stationary processing platform. The FPSO industry has converted hundreds of tankers since the 1970s. Key examples:

4.1 Notable Conversion Projects

FPSO Cidade de Itaguai (MODEC, 2015)

  • Donor vessel: VLCC Alga
  • Conversion yard: MODEC/Sofec consortium, hull work in Asia, topsides integration in Brazil
  • Field: Iracema Norte (Lula), Santos Basin, Brazil
  • Capacity: 150,000 bbl/day oil, 280 MMscf/day gas
  • Water depth: 2,240m
  • Timeline: Achieved first oil July 2015, 5 months ahead of schedule
  • Key lesson: Modular topsides approach enabled parallel fabrication and faster integration

FPSO Prosperity (SBM Offshore / Keppel, 2022-2024)

  • Hull: New-build Fast4Ward hull (not a conversion, but relevant for yard work)
  • Conversion yard: Keppel Shipyard, Singapore
  • Field: Payara, offshore Guyana (ExxonMobil)
  • Capacity: 220,000 bbl/day
  • Hull arrived Keppel: August 2021, entered drydock October 2021
  • Delivery: Less than 4 years from engineering start
  • Key lesson: Keppel Singapore is a proven FPSO integration yard

FPSO Liza Unity (SBM Offshore, 2021-2022)

  • Hull: First Fast4Ward hull
  • Field: Liza Phase 2, offshore Guyana
  • Capacity: 220,000 bbl/day oil, 400 MMscf/day gas, 2 million bbl storage
  • Purchase price (ExxonMobil buyout): ~$1.26 billion
  • Key lesson: Standardized hull + modular topsides reduces delivery time. The purchase price includes all topsides and years of embedded engineering — not comparable to a stripped tanker conversion.

Typical Aframax FPSO Conversions (Various)

  • Cost range: $150M-$400M for conversion work (excluding topsides equipment procurement)
  • Steelwork: 3,000-6,000 tonnes of new steel (includes turret, flare tower, piping supports, module foundations, helideck, accommodation)
  • Duration: 18-30 months yard time for hull conversion; 24-36 months total with topsides integration
  • Man-hours: 3-4 million man-hours for hull conversion alone

4.2 Key Lessons from FPSO Conversions

1. Donor vessel condition is paramount. Steel renewal (replacing corroded plates) can consume 30-50% of hull conversion cost if the tanker is old or poorly maintained. Target a tanker <15 years old with recent special survey.

2. Stability recalculation is non-trivial. Removing distributed liquid cargo weight and adding concentrated topside equipment weight fundamentally changes the vessel's stability characteristics. Full intact and damage stability analysis required.

3. Fatigue life reassessment required. Trading tankers accumulate fatigue damage from wave loading during voyages. The classification society will require a fatigue life assessment for the new operational profile (permanently moored/stationed vs. trading). A 15-year-old tanker with 15 years of trading service may have 50% of its fatigue life consumed.

4. Parallel fabrication is critical for schedule. While the hull is being converted in dry dock, topsides modules (reactor skid, syngas train, switchgear room, etc.) should be fabricated elsewhere and shipped to the yard for integration.

5. Tank inspection and steel renewal. Every cargo tank must be entered, inspected, cleaned, and assessed. Corroded structure is renewed. For The Claw, most cargo tanks will be repurposed (feedstock buffer storage, slag storage, ballast, etc.) — each repurposed tank needs appropriate coating and structural assessment.


5. Shipyard Selection

5.1 Capable Yards — Global Overview

Shipyard / GroupLocationFPSO Track RecordStrengthsWeaknessesLabour Rate (approx.)
Seatrium (formerly Keppel + Sembcorp Marine)Singapore~15% market share. Multiple FPSO conversions including Prosperity integration.World-class quality, deep FPSO experience, strong project management, proximity to classification society officesHighest cost in Asia, capacity constraints from order backlog$25-35/hr
COSCO Shipping Heavy IndustryDalian, Qidong, China~20% market share. Built/converted FPSOs for Modec, SBM, others.Lowest cost, massive capacity, experience with large structuresQuality control variability, communication challenges, IP concerns for novel technology$10-15/hr
CIMC RafflesYantai, ChinaSemi-submersibles and FPSO hulls. Growing FPSO capability.Large deepwater dock, competitive pricingLess FPSO conversion-specific experience than COSCO$10-15/hr
Drydocks WorldDubai, UAE~8% market share 2020-2030. Decade+ of FPSO/FSO conversion experience.Strategic location (between Asia and Europe), competitive pricing, strong conversion track record, handles complex refurbishment projectsSmaller than Chinese yards, limited heavy-lift crane capacity$15-20/hr
Samsung Heavy IndustriesGeoje, South KoreaMajor FPSO builder (primarily new-build).Extremely high quality, advanced automation, strong LNG experienceVery expensive, focused on new-build, conversion work is lower priority$30-40/hr
Hyundai Heavy IndustriesUlsan, South KoreaFPSO new-build capability.Same quality/cost profile as SamsungSame — oriented toward new-build, not conversion$30-40/hr
Damen VerolmeRotterdam, NetherlandsOccasional FPSO/FSO work.European quality, close to classification societies, good for small/medium conversionsVery expensive (European labor rates), limited capacity$50-70/hr

5.2 Recommended Shortlist for The Claw

Tier 1 (Best fit): 1. Drydocks World, Dubai — Best balance of cost, quality, and conversion experience. Strong track record with FPSO refurbishment and conversion. Strategic location. Labor rates are moderate. Has handled novel/non-standard projects. 2. Seatrium, Singapore — Highest quality and deepest FPSO experience. More expensive but lower risk. If budget allows, this is the safest choice.

Tier 2 (Cost-optimized): 3. COSCO Dalian or Qidong — Lowest cost option (potentially 40-50% cheaper than Singapore). Requires strong owner's team supervision and quality assurance presence. Best if budget is the primary constraint.

Not recommended:

  • Korean yards — too expensive for a conversion project, focused on new-build
  • European yards — prohibitively expensive for this scale of work
  • Smaller Asian yards without FPSO track record — too risky for a novel vessel type

5.3 Cost Impact by Yard Location

Using Singapore as the baseline (index 100):

LocationRelative Cost IndexEstimated Total Conversion Cost
Singapore100$55-80M
Dubai75-85$42-68M
China55-65$30-52M
South Korea110-130$60-104M
Europe150-200$82-160M
These are hull conversion costs only, excluding major equipment procurement (PRRS, syngas engine, cranes, etc.), which are priced globally regardless of yard location.


6. Classification & Certification

6.1 Why Classification Matters

A converted vessel operating 1,000nm offshore needs classification society approval for:

  • Insurance (P&I and hull & machinery)
  • Flag state registration
  • Port state control acceptance
  • Regulatory compliance (SOLAS, MARPOL, flag state regulations)
  • Financing/investor confidence

6.2 Class Notation

There is no existing class notation for "plasma processing vessel." The classification society will need to develop a bespoke classification approach, likely building on existing notations:

Likely class notation components:

  • +1A1 (or equivalent) — Hull structural notation for unrestricted service
  • SHIP — Self-propelled vessel
  • EO — Unattended machinery space (if applicable)
  • DYNPOS or POSMOOR — Positioning system notation (if DP or spread mooring fitted)
  • PROD or equivalent — Production/processing notation (adapted from FPSO notation)
  • HELIDECK — Helicopter landing facility
  • CLEAN — Environmental compliance notation
  • Additional qualifiers — Likely a special feature notation for the plasma processing function

6.3 Classification Society Comparison

SocietyFPSO ExperienceNovel Vessel TypesDesign Approval TimelineRecommendation
DNV (Norway)30+ years FPSO classification, market leader in offshoreStrong — has classed novel offshore units, floating LNG, etc. "Alternative Design" framework for novel concepts6-12 months for design approval (AIP), 12-18 months for full approval in parallel with constructionBest choice. Deepest FPSO experience, most flexible framework for novel vessel types, strongest presence in environmental/clean tech maritime.
Lloyd's Register (UK)Extensive FPSO portfolio, especially in West Africa and North SeaGood — classed naval PAWDS systems (relevant precedent — they certified the PyroGenesis plasma system for US Navy)Similar to DNVStrong second choice. The fact that they certified PAWDS for marine use is directly relevant.
ABS (USA)Strong in Gulf of Mexico FPSOs, dominant in US-flagged vesselsGood for US regulatory framework, close to USCGTypically fast for US-flagged projectsWorth considering if US-flagged. Less relevant if foreign-flagged.
Bureau Veritas (France)Strong in West Africa FPSOsAdequateSimilarLower priority for this project.
Recommended: DNV as primary class, with early engagement (Approval in Principle stage) during basic engineering. Lloyd's Register as alternative, especially given their PAWDS certification history.

6.4 Design Approval Process

1. Concept review (2-3 months) — Present concept to class society, identify applicable rules and any gaps requiring special consideration 2. Approval in Principle (AIP) (4-6 months) — Submit basic engineering package, class reviews and issues AIP confirming the concept is feasible within their rules framework 3. Detailed design review (8-12 months, concurrent with detail engineering) — Submit detailed drawings, calculations, specifications. Class reviews and approves each discipline (structural, mechanical, electrical, fire safety, stability, etc.) 4. Plan approval (rolling, concurrent with construction) — Final approved-for-construction drawings 5. Survey during construction — Class surveyor attends key milestones (steel cutting, block erection, equipment installation, commissioning) 6. Inclining experiment and sea trials — Class witnesses final stability verification and operational testing 7. Certificate issuance — Class issues certificate of classification

Total timeline for class approval: 12-18 months from first submission to full plan approval. Runs in parallel with engineering and construction — not a serial addition to the schedule.

Estimated classification fees: $1.5-3M (design review, plan approval, construction surveys, certificates). Higher end if significant "novel technology" review is required for the plasma reactor installation.


7. Retrofit Timeline

Phase Breakdown

PhaseDurationMonths (Cumulative)Key Activities
1. Concept & FEED6-8 months0-8Vessel selection, concept engineering, class AIP, initial cost estimate, shipyard pre-qualification
2. Basic Engineering6-8 months6-16Naval architecture (stability, structural), process engineering (PRRS integration), P&IDs, equipment specifications, procurement specifications. Overlaps with end of Phase 1.
3. Detail Engineering8-12 months12-24Production drawings (structural, piping, electrical, instrumentation), vendor drawing review, construction work packs. Starts while basic engineering is ~60% complete.
4. Long-Lead Procurement6-12 months8-20PRRS reactor (longest lead — 12+ months), syngas engine, cranes, switchgear, helideck. Ordered during basic engineering, delivered to yard during construction.
5. Vessel Purchase & Delivery2-4 months10-14Identify and purchase donor Aframax tanker, pre-purchase condition survey, deliver to conversion yard. Can happen in parallel with engineering.
6. Yard Mobilization & Strip-Out2-3 months14-19Drydock vessel, gas-free and clean cargo tanks, strip out cargo systems, initial steel surveys, begin steel renewal
7. Hull Conversion (Structural)8-12 months16-28Steel renewal, new foundations, bulkheads, deck reinforcement, crane pedestals, helipad structure, accommodation module. The main construction phase.
8. Topsides Installation4-6 months24-34Install PRRS reactor module, syngas cleanup train, syngas engine/generator, switchgear, piping, instrumentation. Overlaps with late hull conversion.
9. Integration & Hook-Up3-4 months28-36Connect all systems, cable pulling, piping tie-ins, instrument calibration, control system programming, fire and safety system integration
10. Commissioning3-4 months30-38System-by-system testing, loop checks, cold commissioning, hot commissioning, reactor first fire, syngas engine first run, safety system testing
11. Sea Trials1-2 months34-40Vessel performance (speed, manoeuvrability), stability verification, equipment operation under sea conditions, class survey completion, flag state inspection
12. Crew Training & Handover1-2 months36-42Operator training on PRRS system, emergency procedures, helicopter operations training

Critical Path

The critical path runs through: Basic Engineering → PRRS Procurement (12+ month lead) → Topsides Installation → Commissioning.

Hull conversion work is substantial but typically not on the critical path because it proceeds in parallel with PRRS fabrication.

Timeline Summary

ScenarioTotal DurationNotes
Aggressive30-34 monthsEverything goes right, experienced yard, pre-qualified vessel, minimal steel renewal, good weather
Realistic36-42 monthsNormal delays, some steel renewal beyond estimate, equipment delivery slippage, commissioning issues
Conservative42-48 monthsFirst-of-its-kind delays, class approval challenges for novel reactor installation, supply chain issues
Working estimate: 36-42 months from FEED start to sea trials.

This aligns with FPSO conversion industry data: 18-30 months of yard time, plus 12-18 months of pre-yard engineering and procurement. The Claw's topsides are simpler than an FPSO (no gas compression, no water injection, no subsea interface), but the PRRS is novel technology requiring more commissioning time.


8. Retrofit Cost Breakdown

8.1 Cost Estimate — Bottom-Up

Based on real FPSO conversion cost data, adjusted for The Claw's simpler topsides but novel processing technology.

CategoryLow EstimateHigh EstimateNotes
Design & Engineering$5M$10MFEED + basic + detail engineering. Novel technology adds cost vs. standard FPSO conversion.
Vessel Purchase$15M$30MSecond-hand Aframax, 10-20 years old. Price highly dependent on market conditions (tanker market was elevated 2022-2024, softening into 2026).
Steelwork & Structural$8M$16M~2,000t new steel at $4,000-8,000/t fabricated and installed (varies by yard location).
Steel Renewal (hull repair)$3M$8MDepends entirely on vessel condition. Budget 200-500t of renewal plate.
PRRS Reactor System$8M$15MPlasma reactor, torches, refractory, controls. Largest single equipment item.
Syngas Cleanup Train$3M$5MCyclone, scrubber, filters, coolers, blower — all industrial standard equipment.
Syngas Engine/Generator$2M$4MJenbacher or equivalent, dual-fuel capable.
Electrical & Instrumentation$4M$8MSwitchgear, MCCs, cable, VFDs, control system, Ex-rated equipment.
Collection Equipment$6M$12MCranes (2x), conveyors, shredder, dewatering, booms, workboats, davits.
Helipad$2M$4MStructure, lighting, fire systems, monitoring.
Accommodation Module$3M$8MPre-fabricated LQ for additional 20-25 persons (only if needed).
Piping$3M$6MProcess piping, utility piping, fire-fighting piping.
Marine Systems Upgrades$2M$4MNavigation upgrade, VSAT, safety equipment, LSA/FFA upgrades.
Coatings & Insulation$1M$3MTank recoating, thermal insulation on hot piping, deck coatings.
Commissioning & Sea Trials$2M$4MIncludes fuel, harbour dues, tug assist, class surveyor attendance.
Classification Fees$1.5M$3MDesign review, plan approval, construction surveys, certificates.
Project Management$3M$5MOwner's team, marine warranty surveyor, third-party inspectors.
Contingency (15-20%)$10M$25MStandard for first-of-a-kind vessel conversion.
TOTAL$82M$170M

8.2 Working Budget Estimate

$100-130M total conversion cost (mid-range estimate, assuming):

  • Vessel purchased for $20-25M (decent condition, <15 years old)
  • Conversion at Drydocks World Dubai or equivalent mid-cost yard
  • ~2,000 tonnes new steelwork, ~300 tonnes steel renewal
  • PRRS system at $10-12M
  • 15% contingency
  • DNV classification

8.3 Cost Context — FPSO Industry Benchmarks

BenchmarkCostSource
Simple FPSO hull conversion (no topsides)$50-100MIndustry average
Full FPSO conversion with topsides$150-700MIndustry range (complexity dependent)
New-build FPSO$1-3BLarge projects (Guyana, Brazil)
Single-hull conversion (simplest)~10% of new-build costSPE/OTC papers
The Claw's conversion falls at the lower end of FPSO conversion costs because:
  • No turret/swivel (FPSO-specific, $30-80M alone)
  • No subsea interface or risers
  • No gas compression train (FPSOs process reservoir gas at high pressure)
  • No oil offloading system
  • Simpler topsides than oil/gas processing
But it includes costs FPSOs don't have:
  • Novel plasma reactor (first marine installation at this scale)
  • Collection systems (no FPSO equivalent)
  • Higher contingency for first-of-a-kind risk

8.4 Cost Breakdown by Percentage

Category% of Total
Vessel purchase18-20%
Structural / steelwork12-15%
Processing equipment (PRRS + cleanup + genset)18-22%
Collection systems7-9%
Electrical & instrumentation5-7%
Piping, marine, coatings5-8%
Accommodation & helipad5-8%
Engineering & management8-10%
Commissioning, class, trials3-5%
Contingency12-18%

Key Risks and Mitigations

RiskImpactMitigation
Vessel condition worse than surveyed+$5-15M steel renewal, +3-6 monthsThorough pre-purchase survey by independent marine surveyor, include class surveyor in inspection
PRRS delivery delayDelays entire topsides installation (critical path)Early engagement with PyroGenesis, consider pre-ordering during FEED phase
Class approval delays for novel reactor+3-6 monthsEarly AIP engagement with DNV, provide comprehensive risk assessment documentation
Syngas quality insufficient for engineReactor doesn't produce consistent syngas quality → engine tripsOver-design cleanup train, dual-fuel engine capability (fall back to diesel)
Yard schedule slipTypical for first-of-a-kind, +10-20% scheduleChoose experienced yard, strong owner's team on-site, milestone-linked payment schedule
Scope creepAdditional systems/features added during engineeringFreeze scope at end of FEED, change order process with cost/schedule impact assessment
Regulatory uncertaintyNo precedent for ocean-going plasma processing vessel in flag state regulationsFlag state engagement during FEED, choose pragmatic flag (Marshall Islands, Bahamas, Panama — experienced with offshore units)

Sources and Data Quality

Real data from industry:

  • FPSO conversion costs ($150-700M range), steelwork tonnages (3,000-6,000t for full Aframax FPSO), labour rates by region, timeline ranges (18-30 months yard time) — from SPE, OTC papers, and industry publications
  • PyroGenesis PRRS containerized at 10.5 TPD (confirmed from Hurlburt Field project), PAWDS at 65 m2 footprint for naval system
  • Jenbacher Type 6 syngas engine range (1.8-4.5 MWe)
  • Specific FPSO projects: Cidade de Itaguai (MODEC), Prosperity and Liza Unity (SBM/Keppel), with real costs and timelines
  • Shipyard market shares and capabilities from offshore industry databases
Estimates flagged as such:
  • PRRS weight (80-150t) — estimated from comparable 10 TPD plasma gasification plants, not from PyroGenesis specification sheet
  • PRRS cost ($8-15M) — extrapolated from PAWDS $5.5M pricing, scaled up
  • Total conversion cost ($100-130M working estimate) — derived from FPSO conversion benchmarks adjusted for simpler topsides but novel technology
  • Individual equipment weights and costs — engineering estimates based on comparable offshore equipment
Data gaps requiring vendor engagement:
  • Exact PRRS 5-10 TPD weight, dimensions, and foundation loads — must come from PyroGenesis
  • Syngas composition from ocean plastic feedstock — determines cleanup train design and engine suitability
  • Specific yard quotes — requires formal RFQ process during FEED
  • Classification fee and timeline — requires formal engagement with DNV or Lloyd's Register