Knowledge Base

Project Timeline — From Today to First Operational Campaign

Draft Medium Research 6,653 words Created Mar 4, 2026

The Claw — Project Timeline & Critical Path Analysis

> Status: Research complete > Last updated: 2026-03-04 > Scope: From today (March 2026) to first operational campaign in the Great Pacific Garbage Patch > Vessel: Converted Aframax tanker, 245m LOA, plasma gasification at 5-10 TPD, operating from Honolulu


Table of Contents

1. Executive Summary 2. Comparable Project Timelines 3. Phase 0: Foundation (Months 0-6) 4. Phase 1: Proof of Concept (Months 3-21) 5. Phase 2: Design & Acquisition (Months 15-30) 6. Phase 3: Conversion & Build (Months 27-48) 7. Phase 4: Commissioning & First Campaign (Months 45-54) 8. Critical Path Analysis 9. Decision Gates — GO/NO-GO Criteria 10. Parallel Workstreams Map 11. Funding Milestones Aligned to Timeline 12. Risk-Adjusted Timeline Scenarios 13. Sources


1. Executive Summary

Three Scenarios

ScenarioFirst Operational CampaignTotal DurationKey Assumptions
Best caseQ3 202942 monthsPoC compressed, hull pre-identified, Chinese shipyard, no regulatory surprises
Expected caseQ1 203154-60 monthsStandard PoC timeline, normal procurement, moderate regulatory iteration
Worst caseQ3 203272-78 monthsPoC delays, PyroGenesis complications, regulatory pushback on London Protocol, shipyard overruns

Why This Takes 4-6 Years

This is not a software project. It combines:

  • Novel technology validation (plasma gasification of ocean plastic — never done before)
  • Marine classification of a novel vessel type (no existing class notation exists)
  • Heavy industrial conversion (comparable to small FPSO conversions: 35 months average)
  • Regulatory navigation of ambiguous international treaties (London Protocol interpretation)
  • Multi-round capital raising ($68-173M total CAPEX)
Every comparable project — Ocean Cleanup (12 years concept to System 03), PyroGenesis PAWDS (11 years from delivery to first deployment), FPSO conversions (35 months contract to first oil) — confirms that 4-6 years from funded start to operations is aggressive but achievable.


2. Comparable Project Timelines

The Ocean Cleanup — System 03

MilestoneDateDuration
Concept (Boyan Slat's TEDx talk)2013
Crowdfunding ($2.2M)2014Year 1
North Sea prototype test (100m segment)2016Year 3
System 001 deployed from San FranciscoSeptember 2018Year 5
System 001 failed, returned to portJanuary 2019Year 6
System 002 "Jenny" deployedJuly 2021Year 8
System 03 transition begins2022Year 9
System 03 fully deployed to GPGPAugust 2023Year 10
50,000 metric tons removed (cumulative)January 2026Year 13
Key lesson: 5 years from funded concept to first deployment, but the first system failed. 10 years to a working full-scale system. The Ocean Cleanup had massive funding ($100M+) and public support. The Claw should assume similar iteration needs.

Applicable to The Claw: The Claw benefits from existing vessel conversion practices (not building from scratch) and proven plasma technology (PyroGenesis PRRS has operated on land). The innovation is integration, not invention. This should compress the timeline vs. Ocean Cleanup's ground-up development.

PyroGenesis PAWDS — Contract to Sea Deployment

MilestoneDateDuration
US Navy evaluates waste management technologies~2001-201110 years evaluation
Factory Acceptance Testing (FAT) in MontrealMay 2011
First PAWDS delivered to CVN-78 shipyardLate 2011
USS Gerald R. Ford launchedNovember 20132 years after delivery
CVN-78 commissionedJuly 20176 years after delivery
First operational deployment with PAWDSOctober 202211 years after delivery
CVN-79 PAWDS deliveredPre-2024
CVN-80/81 two-ship contract ($11.5M)2020
Key lesson: The PAWDS timeline is distorted by aircraft carrier construction schedules, not plasma technology readiness. The plasma system was ready in 2011. For The Claw, the plasma system readiness (post-PoC) is the gating item, not the vessel.

Applicable to The Claw: PyroGenesis built the PAWDS to spec in roughly 8-13 months (engineering design: 8 months, fabrication: 13 months for the military prototype). A civilian marine PRRS unit should take 12-18 months from contract to factory acceptance.

FPSO Tanker Conversions — Industry Average

MetricDurationSource
Contract to first oil (conversion)34-35 monthsIndustry average across multiple projects
Contract to first oil (newbuild)55-57 monthsIndustry average
Standardized hull (SBM Fast4Ward)12 months less than conventionalSBM Offshore program
Range of actual projects15-60 monthsHighly variable by complexity
Key lesson: FPSO conversions average ~35 months from contract award to first production. The Claw's conversion is simpler than a full FPSO (one processing unit vs. a complete oil production facility), but includes novel systems requiring more regulatory scrutiny.

Applicable to The Claw: The conversion itself (steel work, systems installation, outfitting) should take 18-24 months at a competent shipyard. Add 6-12 months for engineering design review with classification society. Total from hull purchase to operational: 24-36 months.

Gaia First — Ocean Waste 2 Energy Vessel

MilestoneDateStatus
Concept announced~2020
UNESCO partnership2021
First funding round sought (EUR 750K)~2022Unknown if closed
Planned maiden voyage2024 (original estimate)Not achieved
Current status2026Still in development
Key lesson: Gaia First has been working on an ocean waste-to-energy vessel for 5+ years and has not yet launched. Their plan to eliminate 90% of the GPGP with 2 ships in 5 years was unrealistic. Under-capitalization appears to be the primary bottleneck.

Applicable to The Claw: Validates that ocean processing vessels require serious capital commitment. A EUR 750K funding target is insufficient. The Claw's $1.5-4.5M PoC budget and $68-173M total CAPEX are more realistic for the scope.

The Manta (SeaCleaners)

MilestoneDateStatus
Concept by Yvan Bourgnon2016
Association founded2016
Vessel design contract~2019
Planned launchOriginally 2024Delayed
Current status2026Under construction, launch TBD
Key lesson: Even with a purpose-built vessel (not a conversion), 7+ years from concept to launch. The Manta is a smaller vessel (56m) with simpler processing (pyrolysis, not plasma). Construction delays are endemic in novel vessel projects.


3. Phase 0: Foundation (Months 0-6)

Calendar: March 2026 - September 2026 Capital required: $500K-$1M (Pre-seed: founder + angels) Purpose: Legal groundwork, team formation, PoC funding secured

Activities

ActivityDurationCostDeliverable
Legal opinion on London Protocol3-6 months$50-100KWritten opinion from specialist maritime law firm (Ince, HFW, Norton Rose Fulbright) on whether plasma gasification constitutes "incineration at sea"
Classification society pre-engagement2-3 months$10-30KInformal consultation with DNV or Lloyd's Register. Identify classification pathway and data requirements for AiP
PyroGenesis engagement1-2 months$5-15KMOU for Stage 2 test campaign access. Begin licensing discussions
Team recruitment (Phase 1 core)Ongoing$50-100KNaval architect, marine engineer, environmental counsel retained
Business plan & pitch deck2-3 months$20-50KInvestor-grade documentation for PoC funding round
Grant applications submitted3-6 months$10-30KARPA-E, NOAA Marine Debris, NRC IRAP (via PyroGenesis)
Verra methodology scoping3-6 months$20-50KDetermine pathway for ocean plastic destruction credits
Advisory board formation1-3 monthsEquity/honorariaMaritime operations, plasma engineering, environmental markets, regulatory

Decision Gate 0: PROCEED TO POC?

GO if:

  • Legal opinion provides a credible pathway (not necessarily definitive approval, but no hard legal barrier)
  • Classification society confirms the concept is classifiable in principle
  • PyroGenesis confirms facility access and willingness to partner
  • PoC funding ($1.5-4.5M) secured or high-confidence commitments
NO-GO if:
  • Legal opinion concludes plasma gasification IS incineration under London Protocol with no viable counter-argument
  • Classification society identifies a fundamental safety barrier that cannot be engineered around
  • PyroGenesis refuses engagement or enters insolvency without alternatives

4. Phase 1: Proof of Concept (Months 3-21)

Calendar: June 2026 - December 2027 Capital required: $1.5-4.5M (Seed round) Purpose: Validate that plasma gasification works on ocean plastic. Produce data for classification society AiP and investor Series A

Stage 1: Feedstock Characterization (Months 3-5)

ActivityDurationCost
Procure 500 kg ocean plastic samples (Oceanworks + 5 Gyres)4-6 weeks$15-50K
Laboratory analysis: proximate, ultimate, calorific value, chlorine, salt, heavy metals, polymer ID4-6 weeks$20-40K
Rinse effectiveness testing2-3 weeks$5-10K
Analysis and reporting2-3 weeks$10-20K
GO/NO-GO Gate 1 (Month 5):
  • Calorific value >= 25 MJ/kg (dry) for 2 of 3 batches
  • Chlorine < 2% after rinse
  • Salt reducible below 0.5%
  • No showstopper heavy metals

Stage 2: Bench-Scale Plasma Testing (Months 5-12)

ActivityDurationCost
PyroGenesis engineering preparation6-8 weeks$50-100K
Feedstock procurement for testing (5+ tonnes via Ocean Cleanup or charter expedition)4-8 weeks$30-80K
Test campaign at PyroGenesis Montreal (PRRS 2 TPD prototype)8-16 weeks$150-400K
25-30 test runs across feedstock batches, moisture levels, feed rates, torch power(included above)
3-5 extended runs at optimal conditions (24-72 hours each)(included above)
Independent laboratory analysis (slag TCLP, emissions, condensate)4-6 weeks$40-100K
Third-party verification of results2-4 weeks$20-50K
Data analysis and investor-grade reporting4-6 weeks$30-70K
GO/NO-GO Gate 2 (Month 12):
  • Net energy ratio > 1.0 at >= 15% moisture for at least one batch
  • Syngas LHV >= 8 MJ/Nm3
  • Dioxin/furan < 0.1 ng TEQ/Nm3
  • Slag passes TCLP (non-hazardous)
  • No catastrophic equipment failure from salt/chlorine

Stage 3: Extended Pilot Campaign (Months 12-21)

ActivityDurationCost
Three extended campaigns (2-4 weeks continuous each)12-16 weeks$400K-1.2M
Pre-processing line build and test (shredder, rinse, centrifuge, dryer)6-8 weeks lead, runs during campaigns$200-600K
Additional feedstock procurement (5-15 tonnes)4-8 weeks$50-200K
Continuous monitoring and reliability engineeringDuration of campaigns$50-150K
Certified emissions stack testingPer campaign$50-150K
Final comprehensive report (investor + regulator + classification society grade)6-8 weeks$50-100K
GO/NO-GO Gate 3 (Month 21):
  • Uptime > 80% across all three campaigns
  • Net energy ratio confirmed > 1.0 at realistic moisture
  • Emissions consistently within MARPOL Annex VI limits
  • No failure requiring > 48 hours repair
  • Pre-processing demonstrates viable feedstock preparation
  • Dataset sufficient for DNV/Lloyd's AiP submission

5. Phase 2: Design & Acquisition (Months 15-30)

Calendar: June 2027 - September 2028 Capital required: $15-30M (Series A) Purpose: Classification society approval, hull acquisition, conversion engineering, PRRS procurement

Note: Phase 2 overlaps with the tail end of Phase 1. Key Phase 2 activities begin during Stage 3 of the PoC, once Gate 2 (bench-scale success) provides sufficient confidence.

Classification Society Pathway

StepDurationTimingCost
Formal AiP submission — concept design, PoC data package, operational profile, hazard identification3-6 monthsMonths 15-21$200-500K
AiP review and issuance — class society evaluates concept, issues AiP (or conditional AiP with requirements)3-6 months from submissionMonths 18-27(included above)
Basic design review — hull structural analysis, stability calcs, fire/safety plans, PRRS integration design, HAZID/HAZOP6-12 monthsMonths 21-33$500K-1M
Class design approval — formal approval of conversion designAt end of basic designMonth 30-33(included above)
Total classification timeline to design approval: 15-21 months from first formal submission

This aligns with the regulatory pathway research (Phase 1: 3-6 months for AiP, Phase 2: 6-12 months for basic design review). The classification process is on the critical path — it must be substantially complete before shipyard conversion begins.

Hull Acquisition

StepDurationTimingNotes
Broker engagement1 monthMonth 18Instruct 3-4 brokers (Clarksons, SSY, Fearnleys, Xclusiv) simultaneously
Market search & shortlisting2-4 monthsMonths 18-22Identify 5-10 candidate 17-22 year old Aframax hulls
Condition surveys2-4 weeks per vesselMonths 22-24Class surveyor + naval architect inspection. Hull thickness gauging, machinery condition, structural assessment
Negotiation & purchase2-3 monthsMonths 24-27MOA signing, deposit, flag transfer, delivery
Drydock inspection4-6 weeksMonth 27-28Full drydock survey, class approval for conversion baseline
Hull cost: $12-25M for 17-22 year old Aframax (current market: elevated but softening for older tonnage)

Key risk: Hull acquisition timing depends on market availability. The search can begin speculatively during PoC Stage 3, but firm commitment requires Series A funding and Gate 2 passage. A 6-month window from search to delivery is realistic; 12 months if the right vessel is not immediately available.

PRRS Plasma Unit Procurement

StepDurationTimingNotes
Licensing agreement with PyroGenesis3-6 months negotiationMonths 15-21Perpetual license, IP escrow, marine application rights
Marine PRRS engineering design8-12 monthsMonths 18-30Marinization: vibration isolation, corrosion protection, class-approved materials, marine electrical
Component procurement6-10 monthsMonths 22-32Graphite electrodes, refractory linings, plasma torches, transformer, cooling system
Factory fabrication8-13 monthsMonths 26-39Assembly at PyroGenesis Montreal or licensed fabricator
Factory Acceptance Testing (FAT)4-6 weeksMonth 39-40Run with test feedstock, verify all parameters
PRRS cost: $15-30M (land-based unit + 20-40% marinization premium)

Critical path note: PRRS procurement is the longest single lead-time item. It MUST begin during PoC Stage 3 (Month 15-18) with preliminary engineering, even before Gate 3. The risk is that Gate 3 fails and the engineering work is wasted ($200-500K). This is an acceptable risk to avoid a 12+ month delay to the overall project.

Parallel During Phase 2

WorkstreamDurationMonths
Flag state selection & registration3-6 months18-24
MARPOL compliance engineeringOngoing18-30
Methanol synthesis feasibility study (if syngas H2:CO ratio supports it)4-6 months18-24
Collection system detailed design6-9 months21-30
Verra methodology development (continues from Phase 0)Ongoing, 2-5 years total0-60
Corporate sponsorship negotiationsOngoing18-36
Crew recruitment planning3-6 months24-30

6. Phase 3: Conversion & Build (Months 27-48)

Calendar: June 2028 - March 2030 Capital required: $50-100M (Series A remainder + DFI debt + blended finance) Purpose: Convert the acquired hull into an operational plasma processing vessel

Shipyard Selection

FactorChinese YardTurkish YardSingapore YardEuropean Yard
Labour costLowestLow-mediumMedium-highHighest
Conversion cost estimate$15-20M$18-25M$25-35M$30-40M
Quality track recordVariable (select carefully)Good for conversionsExcellentExcellent
FPSO conversion experienceExtensive (COSCO, Shanghai Waigaoqiao)LimitedExtensive (Keppel, Sembcorp)Moderate
Classification surveyor accessDNV/LR present at major yardsDNV/LR presentDNV/LR presentDNV/LR headquartered nearby
Proximity to HonoluluCloser than EuropeDistantModerateDistant
Recommendation: Chinese yard (COSCO Dalian, Shanghai Waigaoqiao, or Zhoushan) for cost efficiency, or Singapore (Keppel) for quality and FPSO conversion expertise. Selection depends on Series A budget constraints.

Conversion Timeline

PhaseDurationMonthsKey Activities
Mobilization & strip-out2-3 months27-30Vessel arrives at shipyard. Strip cargo systems (pumps, COW, IGS, cargo heating, manifolds). ~500-800 tonnes removed. Tank cleaning and gas-freeing.
Structural modifications4-6 months30-36Deck reinforcement for processing equipment (800-1,200 tonnes new steel). Reactor foundation (80-120 tonnes). Fire/blast walls (300-500 tonnes). Exhaust stack structure. Tank conversions for ballast, freshwater, waste storage.
Systems installation6-8 months34-42PRRS reactor and gas cleaning installation. Syngas engine/genset installation. Collection system (booms, davits, conveyors, dewatering). Electrical upgrade (1-2 MW new generation). Piping (waste feed, cooling, syngas, fire suppression). Accommodation expansion (28-50 berths). Navigation and comms upgrade.
PRRS installation3-4 months38-42Reactor module lowered into foundation. Torch alignment and connection. Gas cleaning train hookup. Power and cooling connections. Control system integration.
Outfitting & finishing2-3 months42-45Painting, insulation, safety equipment (lifeboats, fire suppression). Helipad installation. HVAC commissioning. Galley and accommodation fit-out.
Harbour trials4-6 weeks45-46All systems tested alongside. PRRS fired with test feedstock. Stability verification (inclining experiment). Safety system tests.
Note: Many of these activities overlap. Structural work and systems installation are partially concurrent. The PRRS can be installed as soon as the reactor foundation is ready, even while other systems work continues.

Total conversion duration: 18-24 months from vessel arrival at shipyard to completion of harbour trials.

This aligns with FPSO conversion benchmarks (35 months contract to first oil includes engineering design time; physical conversion is 18-24 months of that).

Classification During Conversion

ActivityTimingNotes
Detail design reviewThroughout Months 27-42Class surveyors review engineering drawings as they are produced. Iterative approval process.
Construction supervisionThroughout Months 30-45Class surveyor stationed at shipyard. Witnesses critical welding, testing, installations.
PRRS FAT witnessMonth 39-40Class surveyor witnesses factory acceptance test at PyroGenesis
Equipment certificationThroughoutAll major equipment (PRRS, generators, switchboard, fire systems) certified to class standards
Stability booklet approvalMonth 44-45Post-conversion stability calculations approved
Safety equipment surveyMonth 45-46Life-saving, fire-fighting, navigation equipment verified

7. Phase 4: Commissioning & First Campaign (Months 45-54)

Calendar: December 2029 - September 2030 Capital required: Part of Phase 3 build budget + initial OPEX funding ($5-10M) Purpose: Sea trials, transit to Honolulu, first operational campaign in the GPGP

Sea Trials

ActivityDurationMonthsLocation
Builder's sea trials1-2 weeks46Near shipyard
PRRS sea trials (processing while underway or station-keeping)2-4 weeks46-47Near shipyard, controlled conditions
Acceptance trials (owner + class + flag state)1-2 weeks47-48Near shipyard
Defect rectification2-4 weeks48-49Shipyard
Final class surveys and certification2-3 weeks49-50Shipyard

Transit & Mobilization

ActivityDurationMonthsNotes
Transit from shipyard to Honolulu2-4 weeks50-51Depends on shipyard location (China: ~14 days, Europe: ~28 days via Suez/Panama)
Honolulu port setup2-4 weeks51-52Bunkering, provisioning, crew boarding, final inspections. Establish shore-side logistics (slag offloading, fuel supply, crew rotation)
USCG inspection (if US-flagged)1-2 weeks52Coast Guard inspection for vessels operating from US ports
Regulatory clearancesOngoing50-52Flag state operating permit, USCG notification, port state control

First Operational Campaign

ActivityDurationMonthsNotes
Transit Honolulu to GPGP3 days52-53~1,000nm at 14-15 knots
Initial operations (shakedown)14 days53Reduced processing rate, system calibration, crew familiarization
First full campaign28 days53-54Full 28-day operating cycle at 5-10 TPD target
Return to Honolulu3 days54First port call with processed material

First Campaign Success Criteria

MetricTargetMinimum
Days on station2814
Processing throughput5-10 TPD average3 TPD
System uptime> 80%> 60%
Plastic collected and processed140-280 tonnes42 tonnes
Safety incidentsZero seriousZero fatalities
Environmental compliance100% MARPOL100%

8. Critical Path Analysis

The Sequential Chain

The longest sequential dependency chain determines the minimum project duration. Here is the critical path:

CRITICAL PATH (cannot be compressed without parallel risk-taking):

Legal Opinion (3-6 mo) ↓ PoC Stage 1: Feedstock Characterization (2-3 mo) ↓ Gate 1 PoC Stage 2: Bench-Scale Plasma Testing (4-8 mo) ↓ Gate 2 PoC Stage 3: Extended Pilot Campaign (6-12 mo) ↓ Gate 3 AiP Submission + Review (6-12 mo) ← OVERLAPS with Stage 3 tail ↓ Basic Design Review (6-12 mo) ← OVERLAPS with hull search/purchase ↓ Hull Purchase + Delivery to Shipyard (3-6 mo) ↓ Shipyard Conversion (18-24 mo) ← PRRS FAT happens during this window ↓ Sea Trials + Commissioning (3-4 mo) ↓ Transit to Honolulu + First Campaign (2-3 mo)

TOTAL SEQUENTIAL: 53-90 months (4.4-7.5 years) WITH OVERLAPS: 42-60 months (3.5-5 years)

What Blocks What

This Activity......Cannot Begin Until
PoC Stage 2 (bench testing)Gate 1 passed (feedstock viable)
PoC Stage 3 (extended pilot)Gate 2 passed (plasma processing viable)
Formal AiP submissionStage 2 data available (syngas quality, emissions, slag data)
Hull purchase commitmentSeries A funded + Gate 2 passed
PRRS marine engineering contractGate 2 passed + PyroGenesis license signed
Shipyard conversion startHull delivered + Class design approval (at least conditional) + PRRS engineering substantially complete
PRRS installation at shipyardPRRS factory acceptance testing complete
Sea trialsConversion complete + class harbour trial approval
First operational campaignClass certification + flag state operating permit + crew trained

Compression Opportunities (Parallel Risk-Taking)

These activities can run in parallel to compress the timeline, but each carries risk if the preceding gate fails:

Parallel ActivityNormal StartCompressed StartRisk
Classification pre-engagementAfter PoCDuring Phase 0 (Month 1)Low — $10-30K, builds relationships
AiP submissionAfter Stage 3During Stage 3 (Month 15)Low-Medium — uses Stage 2 data, update with Stage 3 data
Hull searchAfter Gate 3During Stage 3 (Month 12)Medium — search is free, commitment requires funding
PRRS marine engineeringAfter Gate 3After Gate 2 (Month 12)Medium — $200-500K at risk if Gate 3 fails
Series A fundraisingAfter Gate 3During Stage 3 (Month 15)Low — use Stage 2 results for preliminary pitch
Corporate sponsor engagementAfter PoCDuring PoC (Month 6)Low — relationship building, no commitments
Recommendation: Execute ALL compression opportunities except PRRS engineering. The cost of speculative work ($50-100K for parallel pre-engagement, search, fundraising prep) is negligible against the 6-12 month time savings. PRRS engineering before Gate 3 is a judgment call — if Stage 2 results are strong, begin preliminary marine engineering.


9. Decision Gates — GO/NO-GO Criteria

Gate 0: Commit to PoC (Month 6)

CriterionGONO-GO
Legal opinionCredible pathway existsHard legal barrier, no counter-argument
ClassificationConcept is classifiableFundamental safety barrier
PyroGenesisFacility access confirmedNo access, no alternatives
Funding$1.5M+ securedCannot raise PoC funding

Gate 1: Feedstock Viable (Month 5)

CriterionGOKILL
Calorific value (dry)>= 25 MJ/kg (2/3 batches)< 20 MJ/kg (all batches)
Chlorine after rinse< 2%> 5%
Salt after rinse< 0.5%> 2% (irreducible)
Heavy metalsNo hazardous classificationSlag would be hazardous waste

Gate 2: Plasma Processing Viable (Month 12)

CriterionGOCONDITIONALKILL
Net energy ratio> 1.50.7-1.5< 0.7
Syngas LHV> 10 MJ/Nm36-10 MJ/Nm3< 6 MJ/Nm3
Dioxin/furan< 0.05 ng TEQ/Nm30.05-0.1> 0.1
Slag TCLPPassFail
Equipment conditionNo salt damageAccelerated corrosion (engineerable)Severe corrosion < 100 hrs

Gate 3: Operational Viability (Month 21)

CriterionGO to Phase 2CONDITIONALKILL
Uptime> 80%60-80%< 60%
Energy ratio (realistic moisture)> 1.0 confirmed0.7-1.0 (supplemental diesel)< 0.7
Emissions vs. MARPOLConsistently within limitsMarginal (needs better gas cleaning)Cannot meet limits
Pre-processingViableNeeds more developmentEnergy-prohibitive
Data sufficiencyEnough for AiPPartial — needs more testingFundamental unknowns remain

Gate 4: Commit to Conversion (Month 27)

CriterionGONO-GO
AiP issuedYes (or conditional AiP with manageable conditions)Refused
Hull acquiredPurchase completed or LOI signedNo suitable hull available
PRRS on orderLicense signed, engineering underwayPyroGenesis cannot deliver
Funding$50M+ secured (combination of equity, debt, grants)Insufficient capital
RegulatoryFlag state engagement positiveFlag state refuses to permit

Gate 5: Proceed to Operations (Month 50)

CriterionGONO-GO
Class certificationCertificate of Class issuedOutstanding class conditions preventing operation
Sea trialsAll acceptance criteria metPRRS fails at sea
RegulatoryOperating permits in handMissing permits
CrewTrained and certifiedInsufficient qualified crew
InsuranceP&I and hull & machinery cover boundCannot obtain insurance

10. Parallel Workstreams Map

Month:  0    3    6    9   12   15   18   21   24   27   30   33   36   39   42   45   48   51   54
        |    |    |    |    |    |    |    |    |    |    |    |    |    |    |    |    |    |    |
LEGAL:  [===Legal Opinion====]
        [=========================Verra Methodology (2-5 year process, continues beyond chart)===...
        [===Flag State Research=====]
                                          [====Flag State Registration====]

POC: [S1==][====Stage 2========][===========Stage 3================] G1 G2 G3

CLASS: [Pre-engage] [====AiP Submission + Review======] [==========Basic Design Review==========] [====Detail Design Review (continues into conversion)====]

HULL: [===Search===][Survey][===Purchase===][Delivery]

PRRS: [===License Negotiation===] [=======Marine Engineering Design===========] [=====Component Procurement======] [=======Fabrication=======][FAT]

SHIPYARD: [Strip][===Structural===] [=====Systems Installation=====] [===PRRS Install===] [Outfitting] [Trials]

FUNDING: [Pre-seed][=====Seed Round=====] [=========Series A============] [============Build Funding (DFI debt + equity)============]

MEDIA: [Brand/Story] [PoC Content] [=====Campaign Building=====][======Launch Campaign=======]

OPS: [=====Crew Recruitment=====] [Honolulu Base Setup] [Transit][FIRST CAMPAIGN]

Key Observations from the Workstream Map

1. The classification pathway is the hidden critical path. While PoC gets all the attention, the AiP + basic design review takes 12-18 months and cannot begin properly until PoC Stage 2 data exists. Starting pre-engagement in Month 1 is essential.

2. PRRS fabrication is the long pole. 18-24 months from engineering start to FAT. If it begins at Month 18 (after Gate 2), FAT is at Month 39-42, which must happen BEFORE installation at the shipyard (Month 38-42). This is razor-thin. Starting preliminary marine engineering at Month 12-15 provides necessary buffer.

3. Hull acquisition is NOT on the critical path — surprisingly. A 17-22 year old Aframax can be purchased in 3-6 months. The hull can arrive at the shipyard while conversion engineering is still being approved, with strip-out work starting immediately.

4. Funding must lead activities by 6-12 months. Series A must close by Month 18-24 to fund hull purchase (Month 24-27) and PRRS procurement (Month 18+). Build funding must close by Month 30-33 to fund conversion start (Month 27-30).


11. Funding Milestones Aligned to Timeline

What Must Exist Before Each Round

RoundAmountTimingPrerequisites for Investors
Pre-seed$500K-1MMonth 0-3Legal opinion commissioned. PyroGenesis MOU. Credible team. Business plan. Advisory board.
Seed$2-5MMonth 3-12Legal opinion received (positive). Gate 1 passed. PyroGenesis test campaign contracted. Grant applications submitted. Preliminary investor interest.
Series A$15-30MMonth 15-24Gate 2 passed (bench-scale success). AiP submitted or in progress. PoC data package (energy balance, emissions, slag). Corporate sponsor LOI ($1M+). Media presence established. Hull candidates identified.
Build (debt + equity)$50-100MMonth 24-36Gate 3 passed (operational viability). AiP issued. Hull purchased. PRRS on order. Class design approval in progress. Revenue projections backed by PoC data. DFI term sheets. Corporate naming rights deal.
OPEX bridge$5-10MMonth 45-50Vessel conversion >80% complete. Sea trials imminent. Operating permits in hand. Crew recruited. First-year OPEX budget locked.

Funding Source Alignment

SourceRoundAmountRationale
Founder + angelsPre-seed$200-500KPersonal commitment, early believers
Schmidt Marine Technology PartnersPre-seed/Seed$100-300KOcean technology validation
CrowdfundingSeed$1-2MPublic validation, media catalyst
ARPA-E / DOE BETOSeed$1-3MWaste-to-energy innovation
NOAA Marine DebrisSeed$500K-2MOcean plastic removal R&D
NRC IRAP / Canada SIFSeed/Series A$500K-10MPyroGenesis partnership leverage
Closed Loop PartnersSeries A$5-10MCircular economy infrastructure
EU Innovation FundSeries A$5-15MWaste-to-energy, medium-scale track
Minderoo FoundationSeries A$2-5MSea the Future alignment
EIB Clean Oceans Initiative 2.0Build$10-50MConcessional debt, $3B target for 2026-2030
IFCBuild$10-30MBlended finance, ocean plastic precedent
Corporate naming rightsBuild$5-15M/yearMulti-year deal, vessel naming
Mega-donor (Benioff/Gebbia/Forrest caliber)Build$10-25MSingle transformative gift
Pre-sold plastic creditsOPEX$2-5MRevenue advance against future operations

12. Risk-Adjusted Timeline Scenarios

Best Case: 42 Months (Q3 2029)

Assumptions:

  • Legal opinion positive within 3 months
  • PoC compressed to 14 months (fast procurement, no equipment issues, PyroGenesis immediately available)
  • Gate 2 results so strong that AiP submission begins at Month 10
  • Hull pre-identified during PoC, purchased immediately after Gate 2
  • PRRS marine engineering begins after Gate 2 (Month 10)
  • Chinese shipyard with aggressive schedule (18 months conversion)
  • No significant regulatory pushback
  • Funding rounds close within 3 months of starting
Month  0: Pre-seed closed. Legal opinion + PoC begin.
Month  3: Gate 1 passed. Stage 2 begins.
Month 10: Gate 2 passed. AiP submitted. Hull search begins. PRRS engineering begins.
Month 14: Gate 3 passed. Hull purchased. Series A closed.
Month 16: AiP issued. Hull arrives at shipyard. Strip-out begins.
Month 18: Basic design review submitted. Build funding securing.
Month 20: PRRS FAT begins at PyroGenesis.
Month 22: PRRS delivered to shipyard. Installation begins.
Month 34: Conversion complete. Sea trials begin.
Month 38: Transit to Honolulu.
Month 42: First operational campaign.

Probability: 10-15%. This requires everything to go right and aggressive parallel execution.

Expected Case: 54-60 Months (Q1-Q3 2031)

Assumptions:

  • Legal opinion takes 5 months (moderate complexity)
  • PoC runs 18 months (standard schedule, one re-test needed in Stage 2)
  • AiP submission at Month 15, issuance at Month 24
  • Hull search takes 6 months, purchase at Month 24
  • PRRS marine engineering begins at Month 15, FAT at Month 39
  • Singapore or Chinese shipyard, 20-month conversion
  • One round of regulatory iteration (flag state questions, class conditions)
  • Each funding round takes 4-6 months to close
  • 3-month schedule slip from unforeseen issues (weather, supply chain, personnel)
Month  0: Pre-seed. Legal opinion + classification pre-engagement begin.
Month  5: Gate 1 passed.
Month 12: Gate 2 passed. AiP submission begins.
Month 15: PRRS marine engineering begins. Hull search begins. Series A fundraising begins.
Month 18: Stage 3 begins. Series A closing.
Month 21: Gate 3 passed. AiP under review.
Month 24: AiP issued (with conditions). Hull purchased. Series A closed.
Month 27: Hull arrives at shipyard. Strip-out begins. Build funding begins.
Month 30: Basic design review approved. Structural work begins. Build funding closing.
Month 39: PRRS FAT complete.
Month 42: PRRS installation at shipyard.
Month 48: Conversion substantially complete. Harbour trials.
Month 51: Sea trials complete. Transit to Honolulu.
Month 54: First operational campaign begins.

Probability: 40-50%. This is the planning target.

Worst Case: 72-78 Months (Q3 2032)

Assumptions:

  • Legal opinion inconclusive — requires second opinion or flag state consultation (+6 months)
  • PoC Stage 2 shows conditional results (net energy ratio 0.7-1.0) — requires extended testing (+6 months)
  • PyroGenesis enters creditor protection during Stage 3 — must secure data, find alternative fabricator (+6-12 months)
  • AiP issued with significant conditions requiring additional engineering (+6 months)
  • Hull market tight — acceptable vessel not available for 12 months
  • Classification society requires HAZOP iteration (+3 months)
  • Shipyard encounters structural surprises during conversion (+4 months)
  • PRRS installation requires modifications for sea conditions discovered during trials (+3 months)
  • Funding rounds take 9-12 months each due to market conditions
Month  0: Pre-seed.
Month  6: Legal opinion inconclusive. Commission second opinion.
Month  9: Gate 1 passed (delayed by feedstock sourcing).
Month 18: Gate 2 — conditional proceed (energy ratio 0.9). Extended testing planned.
Month 24: Extended Stage 2 testing confirms viability with pre-drying.
Month 30: Gate 3 passed (delayed). AiP submission with full data set.
Month 33: PyroGenesis enters creditor protection. IP escrow activated. Alternative fabricator sought.
Month 36: AiP issued with conditions. New PRRS fabrication partner identified.
Month 42: Hull purchased (delayed by market + funding timing).
Month 45: Hull at shipyard. Conversion begins. PRRS engineering restarted with new partner.
Month 57: PRRS FAT complete (new fabricator learning curve).
Month 60: PRRS installation.
Month 66: Conversion complete. Sea trials.
Month 72: Transit to Honolulu (after trial defect rectification).
Month 78: First operational campaign.

Probability: 20-25%. Multiple things must go wrong, but each individual risk is plausible.

Timeline Risk Register

RiskImpact on TimelineProbabilityMitigation
Legal opinion says plasma IS incinerationPROJECT KILL or +12-24 months for treaty interpretationLow (15%)Commission from top-tier maritime firm. Prepare fallback arguments. Engage flag state early.
PyroGenesis bankruptcy+6-12 monthsMedium (30%)IP escrow clause. Maintain relationships with key engineers. Identify alternative fabricators (Plazarium, Advanced Plasma Power).
PoC shows marginal energy balance+6 months extended testingMedium (25%)Pre-define "conditional proceed" criteria. Budget for extended Stage 2.
Classification society imposes conditions+3-6 monthsMedium-High (40%)Pre-engagement in Phase 0. Submit comprehensive data package. Budget for iteration.
Hull market spike / no suitable vessels+3-12 monthsLow-Medium (20%)Begin search early. Consider multiple vessel types (large OSV as alternative). Instruct multiple brokers.
Shipyard conversion overrun+3-6 monthsMedium (35%)Use experienced FPSO conversion yard. Fixed-price contract with LD clauses. Owner's engineer on site.
PRRS integration issues at sea+2-4 monthsMedium (30%)Extended harbour trials. Gradual ramp-up. Budget for post-trial modifications.
Funding delays+3-12 months per roundMedium (30%)Maintain parallel funding tracks. Government grants as bridge. Keep burn rate low during fundraising.

13. Sources

Comparable Project Timelines

PyroGenesis PAWDS Timeline

FPSO Conversion Timelines

Vessel Market & Conversion

Classification Society & Regulatory

Funding & Market

Waste-to-Energy Vessels


Research compiled March 2026. Timelines are estimates grounded in comparable projects and industry benchmarks. Every phase should be replanned as actual data becomes available. The expected case (54-60 months) is the planning baseline; budget and schedule reserves should accommodate the worst case.